Status Completed
Accomplishment 100.00%
Contract Cost ₱89.8M
Contract Duration 210 days

Project Progress

100.00%

Basic Information

Contract ID 25OD0043
Infrastructure Year 2025
Description CONSTRUCTION OF FLOOD CONTROL WALL ALONG THE BANKS OF CREEKS, BARANGAY 171 TIERA NOVA, CALOOCAN CITY

Implementing Office Authorities

Region NCR - National Capital Region
Implementing Office Metro Manila 3rd District Engineering Office
Project Engineer N/A
Project Inspector N/A
Materials Engineer N/A
Approving Authority N/A

Contractor Authorities

Contractor KING EIGHT BUILDERS AND SUPPLY (37325) / KING SKY BUILDERS AND SUPPLY INC., FORMERLY (KING EIGHT BUILDERS AND SUPPLY INC.) (53938)
Project Manager N/A
Project Engineer N/A
Materials Engineer N/A

Financial Information

Source of Funds Regular Infra - GAA 2025 OO-2
Contract Cost ₱89,839,600.64

Contract Duration

Effectivity Date February 13, 2025
Original Expiry Date September 10, 2025
Contract Duration 210 days
Days Remaining Expired (82 days ago)

Status & Progress

Current Status Completed
Accomplishment 100.00%

Record Information

Created At November 26, 2025 12:23 AM
Last Updated November 26, 2025 12:23 AM