Status Completed
Accomplishment 100.00%
Contract Cost ₱89.9M
Contract Duration 300 days

Project Progress

100.00%

Basic Information

Contract ID 25OD0036
Infrastructure Year 2025
Description CONSTRUCTION OF FLOOD CONTROL WALL ALONG THE BANKS OF MATARIK, BARANGAY 176 (PHASE 3), CALOOCAN CITY

Implementing Office Authorities

Region NCR - National Capital Region
Implementing Office Metro Manila 3rd District Engineering Office
Project Engineer N/A
Project Inspector N/A
Materials Engineer N/A
Approving Authority N/A

Contractor Authorities

Contractor PERSAN CONSTRUCTION, INC. (FORMERLY: PERSAN CONST. (2852)
Project Manager N/A
Project Engineer N/A
Materials Engineer N/A

Financial Information

Source of Funds Regular Infra - GAA 2025 OO-2
Contract Cost ₱89,931,184.37

Contract Duration

Effectivity Date February 13, 2025
Original Expiry Date December 09, 2025
Contract Duration 300 days
Days Remaining 7 days remaining

Status & Progress

Current Status Completed
Accomplishment 100.00%

Record Information

Created At November 26, 2025 12:21 AM
Last Updated November 26, 2025 12:21 AM