Basic Information
Contract ID
25OB0239
Infrastructure Year
2025
Description
RETROFITTING/STRENGTHENING OF PERMANENT BRIDGE - C5/ORTIGAS FLYOVER (B03318LZ) ALONG C5 - ORTIGAS FLYOVER
Implementing Office Authorities
Region
NCR - National Capital Region
Implementing Office
Metro Manila 1st District Engineering Office
Project Engineer
N/A
Project Inspector
N/A
Materials Engineer
N/A
Approving Authority
N/A
Contractor Authorities
Contractor
KING SKY BUILDERS AND SUPPLY INC., FORMERLY (KING EIGHT BUILDERS AND SUPPLY INC.) (53938) / C.T. LEONCIO CONSTRUCTION & TRADING (17371)
Project Manager
N/A
Project Engineer
N/A
Materials Engineer
N/A
Financial Information
Source of Funds
Regular Infra - GAA 2025 OO-1
Contract Cost
₱96,500,000.00
Contract Duration
Effectivity Date
March 27, 2025
Original Expiry Date
December 21, 2025
Contract Duration
270 days
Days Remaining
19 days remaining
Status & Progress
Current Status
Completed
Accomplishment
100.00%
Record Information
Created At
November 25, 2025 09:42 PM
Last Updated
November 25, 2025 09:42 PM