Basic Information
Contract ID
25OA0008
Infrastructure Year
2025
Description
CONSTRUCTION OF FLOOD CONTROL STRUCTURE, PHASE 5, BARANGAY TAÑONG TO BARANGAY DAMPALIT, MALABON CITY
Implementing Office Authorities
Region
NCR - National Capital Region
Implementing Office
Malabon-Navotas District Engineering Office
Project Engineer
N/A
Project Inspector
N/A
Materials Engineer
N/A
Approving Authority
N/A
Contractor Authorities
Contractor
WAWAO BUILDERS (46535)
Project Manager
N/A
Project Engineer
N/A
Materials Engineer
N/A
Financial Information
Source of Funds
Regular Infra - GAA 2025 SSP
Contract Cost
₱96,001,714.06
Contract Duration
Effectivity Date
February 20, 2025
Original Expiry Date
December 16, 2025
Contract Duration
300 days
Days Remaining
14 days remaining
Status & Progress
Current Status
On-Going
Accomplishment
91.46%
Record Information
Created At
November 25, 2025 09:35 PM
Last Updated
November 25, 2025 09:35 PM