Status On-Going
Accomplishment 4.18%
Contract Cost ₱236.3M
Contract Duration 360 days

Project Progress

4.18%

Basic Information

Contract ID 25OA0095
Infrastructure Year 2025
Description REHABILITATION (COMPLETION) OF BANGKULASI PUMPING STATION, NAVOTAS CITY

Implementing Office Authorities

Region NCR - National Capital Region
Implementing Office Malabon-Navotas District Engineering Office
Project Engineer N/A
Project Inspector N/A
Materials Engineer N/A
Approving Authority N/A

Contractor Authorities

Contractor ANORE CONSTRUCTION (34048)
Project Manager N/A
Project Engineer N/A
Materials Engineer N/A

Financial Information

Source of Funds Regular Infra - GAA 2025 OO-2
Contract Cost ₱236,349,929.24

Contract Duration

Effectivity Date July 24, 2025
Original Expiry Date July 18, 2026
Contract Duration 360 days
Days Remaining 228 days remaining

Status & Progress

Current Status On-Going
Accomplishment 4.18%

Record Information

Created At November 25, 2025 09:33 PM
Last Updated November 25, 2025 09:33 PM