Basic Information
Contract ID
25OI0114
Infrastructure Year
2025
Description
CONSTRUCTION OF FLOOD CONTROL STRUCTURES AND OTHER IMPROVEMENTS AT BARANGAYS TALON 1 TO TALON 3, LAS PINAS CITY
Implementing Office Authorities
Region
NCR - National Capital Region
Implementing Office
Las Piñas-Muntinlupa District Engineering Office
Project Engineer
N/A
Project Inspector
N/A
Materials Engineer
N/A
Approving Authority
N/A
Contractor Authorities
Contractor
I&E CONSTRUCTION CORPORATION (FORMERLY: I&E CONSTR (10410)
Project Manager
N/A
Project Engineer
N/A
Materials Engineer
N/A
Financial Information
Source of Funds
Regular Infra - GAA 2025 SSP
Contract Cost
₱218,293,466.80
Contract Duration
Effectivity Date
April 30, 2025
Original Expiry Date
March 25, 2026
Contract Duration
330 days
Days Remaining
113 days remaining
Status & Progress
Current Status
On-Going
Accomplishment
25.03%
Record Information
Created At
November 25, 2025 09:24 PM
Last Updated
November 25, 2025 09:24 PM