Status Completed
Accomplishment 100.00%
Contract Cost ₱9.7M
Contract Duration 93 days

Project Progress

100.00%

Basic Information

Contract ID 25PI0039
Infrastructure Year 2025
Description CONSTRUCTION OF FLOOD CONTROL STRUCURE ALONG CHICO RIVER, SITIO CHEKA-A, BONTOC, MOUNTAIN PROVINCE

Implementing Office Authorities

Region CAR - Cordillera Administrative Region
Implementing Office Mountain Province 1st District Engineering Office
Project Engineer N/A
Project Inspector N/A
Materials Engineer N/A
Approving Authority N/A

Contractor Authorities

Contractor AFEW CONSTRUCTION (45634)
Project Manager N/A
Project Engineer N/A
Materials Engineer N/A

Financial Information

Source of Funds Regular Infra - GAA 2025 OO-2
Contract Cost ₱9,701,999.90

Contract Duration

Effectivity Date February 27, 2025
Original Expiry Date May 30, 2025
Contract Duration 93 days
Days Remaining Expired (185 days ago)

Status & Progress

Current Status Completed
Accomplishment 100.00%

Record Information

Created At November 25, 2025 08:14 PM
Last Updated November 25, 2025 08:14 PM