Status On-Going
Accomplishment 12.10%
Contract Cost ₱9.7M
Contract Duration 245 days

Project Progress

12.10%

Basic Information

Contract ID 25P00005
Infrastructure Year 2025
Description CONSTRUCTION OF ROAD, DATIL-NANGONUGAN ACCESS, BARANGAY POBLACION, SAGADA, MOUNTAIN PROVINCE

Implementing Office Authorities

Region CAR - Cordillera Administrative Region
Implementing Office Cordillera Administrative Region
Project Engineer N/A
Project Inspector N/A
Materials Engineer N/A
Approving Authority N/A

Contractor Authorities

Contractor JAH-ZONE CONSTRUCTION (55024)
Project Manager N/A
Project Engineer N/A
Materials Engineer N/A

Financial Information

Source of Funds Regular Infra - GAA 2025 SSP
Contract Cost ₱9,749,448.75

Contract Duration

Effectivity Date April 03, 2025
Original Expiry Date December 03, 2025
Contract Duration 245 days
Revised Contract Duration 305 days
Revised Expiry Date February 01, 2026
Days Remaining 61 days remaining

Suspension & Extension

Suspension Date October 01, 2025
Resumption Date November 29, 2025
Suspension Duration 60 days
Reason for Delay/Suspension Suspended due to RROW Problem
Extension Duration 60 days
Revised Expiry Date February 01, 2026

Status & Progress

Current Status On-Going
Accomplishment 12.10%

Record Information

Created At November 22, 2025 08:59 PM
Last Updated November 25, 2025 01:44 PM