Basic Information
Contract ID
25PF0031
Infrastructure Year
2025
Description
REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS: GOV. BADO DANGWA NATIONAL ROAD - K0291+280 - K0291+430, K0291+670 - K0291+770, K0291+875 - K0292+080, K0291+290 - K0292+364, K0292+405 - K0292+445, K0292+630 - K0292+900, K02
Implementing Office Authorities
Region
CAR - Cordillera Administrative Region
Implementing Office
Benguet 2nd District Engineering Office
Project Engineer
N/A
Project Inspector
N/A
Materials Engineer
N/A
Approving Authority
N/A
Contractor Authorities
Contractor
FAMILY CIRCLE CONSTRUCTION (32608)
Project Manager
N/A
Project Engineer
N/A
Materials Engineer
N/A
Financial Information
Source of Funds
Regular Infra - GAA 2025 OO-1
Contract Cost
₱53,183,783.05
Contract Duration
Effectivity Date
April 07, 2025
Original Expiry Date
December 25, 2025
Contract Duration
263 days
Days Remaining
23 days remaining
Status & Progress
Current Status
On-Going
Accomplishment
55.00%
Record Information
Created At
November 25, 2025 07:28 PM
Last Updated
November 25, 2025 07:28 PM