Status On-Going
Accomplishment 80.24%
Contract Cost ₱58.0M
Contract Duration 215 days

Project Progress

80.24%

Basic Information

Contract ID 25P00002
Infrastructure Year 2025
Description CONSTRUCTION OF ROAD, ABINUAN - NATTUM - ALIMIT, MAYOYAO, IFUGAO

Implementing Office Authorities

Region CAR - Cordillera Administrative Region
Implementing Office Cordillera Administrative Region
Project Engineer N/A
Project Inspector N/A
Materials Engineer N/A
Approving Authority N/A

Contractor Authorities

Contractor DJY CONSTRUCTION (35651)
Project Manager N/A
Project Engineer N/A
Materials Engineer N/A

Financial Information

Source of Funds Regular Infra - GAA 2025 SSP
Contract Cost ₱57,953,458.96

Contract Duration

Effectivity Date April 10, 2025
Original Expiry Date November 10, 2025
Contract Duration 215 days
Days Remaining Expired (21 days ago)

Status & Progress

Current Status On-Going
Accomplishment 80.24%

Record Information

Created At November 22, 2025 08:54 PM
Last Updated November 22, 2025 08:54 PM