Status On-Going
Accomplishment 91.09%
Contract Cost ₱29.3M
Contract Duration 190 days

Project Progress

91.09%

Basic Information

Contract ID 25JE0023
Infrastructure Year 2025
Description SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) CONSTRUCTION OF ROAD, DUMINGAG- KATIPUNAN ROAD, NRJ BARANGAY UPPER LANDING- BARANGAY DILUD- BARANGAY SAAD- BARANGAY KATIPUNAN, DUMINGAG, ZAMBOANGA DEL SUR

Implementing Office Authorities

Region Region IX - Zamboanga Peninsula
Implementing Office Zamboanga del Sur 1st District Engineering Office
Project Engineer N/A
Project Inspector N/A
Materials Engineer N/A
Approving Authority N/A

Contractor Authorities

Contractor SEVERS CONSTRUCTION & SUPPLIES & REALTY DEVELOPMENT (41004)
Project Manager N/A
Project Engineer N/A
Materials Engineer N/A

Financial Information

Source of Funds Regular Infra - GAA 2025 SSP
Contract Cost ₱29,349,997.22

Contract Duration

Effectivity Date April 01, 2025
Original Expiry Date October 07, 2025
Contract Duration 190 days
Days Remaining Expired (55 days ago)

Status & Progress

Current Status On-Going
Accomplishment 91.09%

Record Information

Created At November 27, 2025 01:42 AM
Last Updated November 27, 2025 01:42 AM