Status Suspended
Accomplishment 0.00%
Contract Cost ₱9.8M
Contract Duration 130 days

Project Progress

0.00%

Basic Information

Contract ID 25JE0029
Infrastructure Year 2025
Description SPECIAL ROAD FUND- MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239:INSTALLATION/ APPLICATION OF ROAD SAFETY FACILITIES (ROADWAY LIGHTING) ALONG PAGADIAN CITY AIRPORT RD.- K1664+(-687)- K1664+260, K1664+(-890)- K1664+(-687), K1664+(-960)- K1664+(-890)

Implementing Office Authorities

Region Region IX - Zamboanga Peninsula
Implementing Office Zamboanga del Sur 1st District Engineering Office
Project Engineer John Roger Gallega
Project Inspector Anecito Tañola
Materials Engineer Roel Acedillo
Approving Authority Pablo L. Escuadro, MPA

Contractor Authorities

Contractor ZMS CONST. & DEV. CORP. (FORMERLY:ZMS CONSTRUCTION (10471)
Project Manager Jesus A. Maniago Jr.
Project Engineer Ronnie B. Nayve
Materials Engineer Reynaldo B. Sansan

Financial Information

Source of Funds Regular Infra - GAA 2025 SSP
Contract Cost ₱9,790,001.69

Contract Duration

Effectivity Date February 14, 2025
Original Expiry Date June 23, 2025
Contract Duration 130 days
Days Remaining Expired (161 days ago)

Suspension & Extension

Suspension Date March 02, 2025
Reason for Delay/Suspension Work Suspension Order No. 1 - Due to absence of CAAP Permit

Status & Progress

Current Status Suspended
Accomplishment 0.00%

Record Information

Created At November 27, 2025 01:31 AM
Last Updated November 27, 2025 01:31 AM