Basic Information
Contract ID
25JE0010
Infrastructure Year
2025
Description
SUSTAINABLE INFASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) CONSTRUCTION OF ROAD, BARANGAY NANGAN- NANGAN- BARANGAY LISON VALLEY- BARANGAY LOURDES- BARANGAY LOWER SIBATANG- NRJ BARANGAY MACASING, TIGBAO AND PAGADIAN CITY, ZAMBOANGA DEL SUR
Implementing Office Authorities
Region
Region IX - Zamboanga Peninsula
Implementing Office
Zamboanga del Sur 1st District Engineering Office
Project Engineer
Ellenita M. Castulo
Project Inspector
Anecito M. Tañola
Materials Engineer
Mely D. Diodoos
Approving Authority
Pablo L. Escuadro, MPA
Contractor Authorities
Contractor
ZMS CONST. & DEV. CORP. (FORMERLY:ZMS CONSTRUCTION (10471)
Project Manager
Jesus A. Maniago Jr.
Project Engineer
Reynaldo B. Sansan
Materials Engineer
Aljie S. Cañete
Financial Information
Source of Funds
Regular Infra - GAA 2025 SSP
Contract Cost
₱39,174,545.59
Contract Duration
Effectivity Date
February 14, 2025
Original Expiry Date
September 16, 2025
Contract Duration
215 days
Revised Contract Duration
305 days
Revised Expiry Date
December 15, 2025
Days Remaining
13 days remaining
Suspension & Extension
Suspension Date
March 17, 2025
Resumption Date
June 14, 2025
Suspension Duration
90 days
Reason for Delay/Suspension
Work Suspension Order No. 1 - Due to Road Right of Way (RROW) Problem
Further delays brought by Unfavorable Weather Condition
Extension Duration
90 days
Revised Expiry Date
December 15, 2025
Status & Progress
Current Status
On-Going
Accomplishment
50.00%