Status On-Going
Accomplishment 50.00%
Contract Cost ₱39.2M
Contract Duration 215 days

Project Progress

50.00%

Basic Information

Contract ID 25JE0010
Infrastructure Year 2025
Description SUSTAINABLE INFASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) CONSTRUCTION OF ROAD, BARANGAY NANGAN- NANGAN- BARANGAY LISON VALLEY- BARANGAY LOURDES- BARANGAY LOWER SIBATANG- NRJ BARANGAY MACASING, TIGBAO AND PAGADIAN CITY, ZAMBOANGA DEL SUR

Implementing Office Authorities

Region Region IX - Zamboanga Peninsula
Implementing Office Zamboanga del Sur 1st District Engineering Office
Project Engineer Ellenita M. Castulo
Project Inspector Anecito M. Tañola
Materials Engineer Mely D. Diodoos
Approving Authority Pablo L. Escuadro, MPA

Contractor Authorities

Contractor ZMS CONST. & DEV. CORP. (FORMERLY:ZMS CONSTRUCTION (10471)
Project Manager Jesus A. Maniago Jr.
Project Engineer Reynaldo B. Sansan
Materials Engineer Aljie S. Cañete

Financial Information

Source of Funds Regular Infra - GAA 2025 SSP
Contract Cost ₱39,174,545.59

Contract Duration

Effectivity Date February 14, 2025
Original Expiry Date September 16, 2025
Contract Duration 215 days
Revised Contract Duration 305 days
Revised Expiry Date December 15, 2025
Days Remaining 13 days remaining

Suspension & Extension

Suspension Date March 17, 2025
Resumption Date June 14, 2025
Suspension Duration 90 days
Reason for Delay/Suspension Work Suspension Order No. 1 - Due to Road Right of Way (RROW) Problem
Further delays brought by Unfavorable Weather Condition
Extension Duration 90 days
Revised Expiry Date December 15, 2025

Status & Progress

Current Status On-Going
Accomplishment 50.00%

Record Information

Created At November 26, 2025 01:47 PM
Last Updated November 26, 2025 01:47 PM