Status On-Going
Accomplishment 54.63%
Contract Cost ₱113.5M
Contract Duration 330 days

Project Progress

54.63%

Basic Information

Contract ID 25PC0001
Infrastructure Year 2025
Description ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF MISSING LINKS/ NEW ROADS - PIDDIG - CARASI - CALANASAN ROAD (CALANASAN SIDE), PACKAGE 2, APAYAO

Implementing Office Authorities

Region CAR - Cordillera Administrative Region
Implementing Office Apayao 2nd District Engineering Office
Project Engineer N/A
Project Inspector N/A
Materials Engineer N/A
Approving Authority N/A

Contractor Authorities

Contractor BHM CONSTRUCTION (30724)
Project Manager N/A
Project Engineer N/A
Materials Engineer N/A

Financial Information

Source of Funds Regular Infra - GAA 2025 OO-1
Contract Cost ₱113,484,000.00

Contract Duration

Effectivity Date April 03, 2025
Original Expiry Date February 26, 2026
Contract Duration 330 days
Days Remaining 86 days remaining

Status & Progress

Current Status On-Going
Accomplishment 54.63%

Record Information

Created At November 25, 2025 02:45 PM
Last Updated November 25, 2025 02:45 PM