Status Suspended
Accomplishment 70.00%
Contract Cost ₱9.8M
Contract Duration 90 days

Project Progress

70.00%

Basic Information

Contract ID 25JE0003
Infrastructure Year 2025
Description CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS NRJ PAGADIAN CITY- ZAMBOANGA CITY ROAD LEADING TO PALPALAN PEAK, PAGADIAN CITY, ZAMBOANGA DEL SUR

Implementing Office Authorities

Region Region IX - Zamboanga Peninsula
Implementing Office Zamboanga del Sur 1st District Engineering Office
Project Engineer Ellenita M. Castulo
Project Inspector Anecito M. Tañola
Materials Engineer Mely D. Diodoos
Approving Authority Pablo L. Escuadro, MPA

Contractor Authorities

Contractor GAF TRADING & CONSTRUCTION (32865)
Project Manager G Lance Andrew C. Fuertes
Project Engineer Ana Liza C. Fuertes
Materials Engineer Reynaldo B. Sansan

Financial Information

Source of Funds Regular Infra - GAA 2025 CP
Contract Cost ₱9,795,000.00

Contract Duration

Effectivity Date March 28, 2025
Original Expiry Date June 25, 2025
Contract Duration 90 days
Revised Contract Duration 180 days
Revised Expiry Date September 23, 2025
Days Remaining Expired (69 days ago)

Suspension & Extension

Suspension Date April 28, 2025
Reason for Delay/Suspension Suspension Order No.1 - RROW Problem in Section I (April 28,2025 - July 25, 2025)
Suspension Order No. 2 - RROW Problem in Section II (September 12, 2025-present)
Extension Duration 90 days
Revised Expiry Date September 23, 2025

Status & Progress

Current Status Suspended
Accomplishment 70.00%

Record Information

Created At November 26, 2025 01:22 PM
Last Updated November 27, 2025 01:48 AM