Status Completed
Accomplishment 100.00%
Contract Cost ₱4.9M
Contract Duration 50 days

Project Progress

100.00%

Basic Information

Contract ID 25JE0001
Infrastructure Year 2025
Description BASIC INFRASTRUCTURE PROGRAM (BIP) CONSTRUCTION OF ROAD, BARANGAY DAO, PAGADIAN CITY, ZAMBOANGA DEL SUR

Implementing Office Authorities

Region Region IX - Zamboanga Peninsula
Implementing Office Zamboanga del Sur 1st District Engineering Office
Project Engineer Ellenita M. Castulo
Project Inspector Anecito M. Tañola
Materials Engineer Roel L. Acedillo
Approving Authority Pablo L. Escuadro, MPA

Contractor Authorities

Contractor ZMS CONST. & DEV. CORP. (FORMERLY:ZMS CONSTRUCTION (10471)
Project Manager Jesus A. Maniago Jr.
Project Engineer N/A
Materials Engineer N/A

Financial Information

Source of Funds Regular Infra - GAA 2025 SSP
Contract Cost ₱4,944,885.97

Contract Duration

Effectivity Date February 14, 2025
Original Expiry Date April 04, 2025
Contract Duration 50 days
Revised Contract Duration 139 days
Revised Expiry Date July 02, 2025
Days Remaining Expired (152 days ago)

Suspension & Extension

Suspension Date March 17, 2025
Resumption Date June 13, 2025
Suspension Duration 89 days
Reason for Delay/Suspension Suspended due to Road Right-of-Way (RROW) Problem
Extension Duration 89 days
Revised Expiry Date July 02, 2025

Status & Progress

Current Status Completed
Accomplishment 100.00%

Record Information

Created At November 26, 2025 01:01 PM
Last Updated November 26, 2025 01:01 PM