Basic Information
Contract ID
25BI0017
Infrastructure Year
2025
Description
ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS FLOOD MANAGEMENT PROGRAM CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM CONSTRUCTION OF SAN FERNANDO FLOOD CONTROL STRUCTURE ALONG
Implementing Office Authorities
Region
Region II - Cagayan Valley
Implementing Office
Nueva Vizcaya District Engineering Office
Project Engineer
N/A
Project Inspector
N/A
Materials Engineer
N/A
Approving Authority
N/A
Contractor Authorities
Contractor
R.O. BUILDERS & DEVELOPMENT CORPORATION (22393)
Project Manager
N/A
Project Engineer
N/A
Materials Engineer
N/A
Financial Information
Source of Funds
Regular Infra - GAA 2025 OO-2
Contract Cost
₱48,127,425.03
Contract Duration
Effectivity Date
February 28, 2025
Original Expiry Date
October 11, 2025
Contract Duration
226 days
Days Remaining
Expired (51 days ago)
Status & Progress
Current Status
Completed
Accomplishment
100.00%