Basic Information
Contract ID
25PC0015
Infrastructure Year
2025
Description
OO2: PROTECT LIVES & PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROG-CONS/REHAB OF FLOOD MITIGATION FACILITIES W/IN MAJOR RIVER BASINS & PRINCIPAL RIVERS-CONS OF FLOOD CONTROL STRUCT ,APAYAO-ABULUG RIVER BASIN,SWAN SECTION, STA. 36+566-STA. 37+121
Implementing Office Authorities
Region
CAR - Cordillera Administrative Region
Implementing Office
Apayao 2nd District Engineering Office
Project Engineer
N/A
Project Inspector
N/A
Materials Engineer
N/A
Approving Authority
N/A
Contractor Authorities
Contractor
ISNAG BUILDERS & DEV'T. CORPORATION (33781) / GOLDRICH CONSTRUCTION & TRADING (16489)
Project Manager
N/A
Project Engineer
N/A
Materials Engineer
N/A
Financial Information
Source of Funds
Regular Infra - GAA 2025 OO-2
Contract Cost
₱141,829,674.53
Contract Duration
Effectivity Date
April 03, 2025
Original Expiry Date
February 26, 2026
Contract Duration
330 days
Days Remaining
86 days remaining
Status & Progress
Current Status
On-Going
Accomplishment
69.82%
Record Information
Created At
November 25, 2025 02:36 PM
Last Updated
November 25, 2025 02:36 PM