Status On-Going
Accomplishment 12.68%
Contract Cost ₱141.7M
Contract Duration 329 days

Project Progress

12.68%

Basic Information

Contract ID 25B00022
Infrastructure Year 2025
Description OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - TUGUEGARAO - SOLANA DIVERSION ROAD (TUGUEGARAO - SOLANA BRIDGE AND APPROACHES), PACKAGE 2, CAGAYAN

Implementing Office Authorities

Region Region II - Cagayan Valley
Implementing Office Region II
Project Engineer N/A
Project Inspector N/A
Materials Engineer N/A
Approving Authority N/A

Contractor Authorities

Contractor DOUBLE J1908 CONSTRUCTION (44337)
Project Manager N/A
Project Engineer N/A
Materials Engineer N/A

Financial Information

Source of Funds Regular Infra - GAA 2025 OO-1
Contract Cost ₱141,706,325.34

Contract Duration

Effectivity Date April 10, 2025
Original Expiry Date March 04, 2026
Contract Duration 329 days
Days Remaining 92 days remaining

Status & Progress

Current Status On-Going
Accomplishment 12.68%

Record Information

Created At November 26, 2025 04:34 AM
Last Updated November 26, 2025 04:34 AM