Status Completed
Accomplishment 100.00%
Contract Cost ₱46.8M
Contract Duration 187 days

Project Progress

100.00%

Basic Information

Contract ID 25AF0053
Infrastructure Year 2025
Description CONST/REHAB OF FLOOD CONTROL MIT. FACILITIES W/IN MAJOR BASINS AND PRINCIPAL RIVERS, CONST. OF FLOOD CONTROL STRUCTURE ALONG BAUANG RIVER BASIN, PACKAGE 1, BRGY. GUSING NORTE, NAG. LU

Implementing Office Authorities

Region Region I - Ilocos Region
Implementing Office La Union 2nd District Engineering Office
Project Engineer N/A
Project Inspector N/A
Materials Engineer N/A
Approving Authority N/A

Contractor Authorities

Contractor VILLAR GENERAL CONSTRUCTION AND SUPPLIES (22540)
Project Manager N/A
Project Engineer N/A
Materials Engineer N/A

Financial Information

Source of Funds Regular Infra - GAA 2025 OO-2
Contract Cost ₱46,802,501.17

Contract Duration

Effectivity Date May 14, 2025
Original Expiry Date November 16, 2025
Contract Duration 187 days
Days Remaining Expired (15 days ago)

Status & Progress

Current Status Completed
Accomplishment 100.00%

Record Information

Created At November 26, 2025 04:19 AM
Last Updated November 26, 2025 04:19 AM