Status On-Going
Accomplishment 94.46%
Contract Cost ₱51.5M
Contract Duration 120 days

Project Progress

94.46%

Basic Information

Contract ID 25AD0046
Infrastructure Year 2025
Description INSTALLATION/APPLICATION OF ROAD SAFETY FACILITIES (ROADWAY LIGHTING) ALONG MANILA NORTH ROAD -K0383+000-K0386+419

Implementing Office Authorities

Region Region I - Ilocos Region
Implementing Office Ilocos Sur 2nd District Engineering Office
Project Engineer N/A
Project Inspector N/A
Materials Engineer N/A
Approving Authority N/A

Contractor Authorities

Contractor EGB CONSTRUCTION CORPORATION (FORMERLY: EGB CONSTRUCTION) (13722)
Project Manager N/A
Project Engineer N/A
Materials Engineer N/A

Financial Information

Source of Funds Regular Infra - GAA 2025 SSP
Contract Cost ₱51,471,602.30

Contract Duration

Effectivity Date February 17, 2025
Original Expiry Date June 16, 2025
Contract Duration 120 days
Days Remaining Expired (168 days ago)

Status & Progress

Current Status On-Going
Accomplishment 94.46%

Record Information

Created At November 26, 2025 04:03 AM
Last Updated November 26, 2025 04:03 AM