Status On-Going
Accomplishment 71.42%
Contract Cost ₱74.9M
Contract Duration 234 days

Project Progress

71.42%

Basic Information

Contract ID 25AD0042
Infrastructure Year 2025
Description CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG AMBURAYAN RIVER, STA. 0+000 - STA. 0+780, SUGPON, ILOCOS SUR

Implementing Office Authorities

Region Region I - Ilocos Region
Implementing Office Ilocos Sur 2nd District Engineering Office
Project Engineer N/A
Project Inspector N/A
Materials Engineer N/A
Approving Authority N/A

Contractor Authorities

Contractor FIRST NORTHWAY DEVELOPMENT & CONSTRUCTION CORP. (11645)
Project Manager N/A
Project Engineer N/A
Materials Engineer N/A

Financial Information

Source of Funds Regular Infra - GAA 2025 OO-2
Contract Cost ₱74,883,461.31

Contract Duration

Effectivity Date February 17, 2025
Original Expiry Date October 08, 2025
Contract Duration 234 days
Days Remaining Expired (54 days ago)

Status & Progress

Current Status On-Going
Accomplishment 71.42%

Record Information

Created At November 26, 2025 04:02 AM
Last Updated November 26, 2025 04:02 AM