Status Completed
Accomplishment 100.00%
Contract Cost ₱14.3M
Contract Duration 116 days

Project Progress

100.00%

Basic Information

Contract ID 25AD0048
Infrastructure Year 2025
Description CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS- CONSTRUCTION OF FLOOD PROTECTION WORKS AT SUYO- TAGUDIN-SANTA CRUZ NIS, SUYO, ILOCOS SUR

Implementing Office Authorities

Region Region I - Ilocos Region
Implementing Office Ilocos Sur 2nd District Engineering Office
Project Engineer N/A
Project Inspector N/A
Materials Engineer N/A
Approving Authority N/A

Contractor Authorities

Contractor FIRST NORTHWAY DEVELOPMENT & CONSTRUCTION CORP. (11645)
Project Manager N/A
Project Engineer N/A
Materials Engineer N/A

Financial Information

Source of Funds Regular Infra - GAA 2025 OO-2
Contract Cost ₱14,258,411.70

Contract Duration

Effectivity Date February 10, 2025
Original Expiry Date June 05, 2025
Contract Duration 116 days
Days Remaining Expired (179 days ago)

Status & Progress

Current Status Completed
Accomplishment 100.00%

Record Information

Created At November 26, 2025 04:00 AM
Last Updated November 26, 2025 04:00 AM