Status On-Going
Accomplishment 24.74%
Contract Cost ₱33.6M
Contract Duration 195 days

Project Progress

24.74%

Basic Information

Contract ID 25AB0117
Infrastructure Year 2025
Description BIP - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES,CONSTRUCTION OF 12 CLASSROOMS - ACADEMIC BUILDING, MARIANO MARCOS STATE UNIVERSITY - CURRIMAO CAMPUS, CURRIMAO, ILOCOS NORTE

Implementing Office Authorities

Region Region I - Ilocos Region
Implementing Office Ilocos Norte 2nd District Engineering Office
Project Engineer N/A
Project Inspector N/A
Materials Engineer N/A
Approving Authority N/A

Contractor Authorities

Contractor AJ TAYLAN CONSTRUCTION CORPORATION (2336)
Project Manager N/A
Project Engineer N/A
Materials Engineer N/A

Financial Information

Source of Funds Regular Infra - GAA 2025 SSP
Contract Cost ₱33,576,108.50

Contract Duration

Effectivity Date June 04, 2025
Original Expiry Date December 15, 2025
Contract Duration 195 days
Days Remaining 13 days remaining

Status & Progress

Current Status On-Going
Accomplishment 24.74%

Record Information

Created At November 26, 2025 03:47 AM
Last Updated November 26, 2025 03:47 AM