Status Completed
Accomplishment 100.00%
Contract Cost ₱37.6M
Contract Duration 200 days

Project Progress

100.00%

Basic Information

Contract ID 25AA0136
Infrastructure Year 2025
Description FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF SEAWALL, BARANGAY BINSANG, PASUQUIN, ILOCOS NORTE

Implementing Office Authorities

Region Region I - Ilocos Region
Implementing Office Ilocos Norte 1st District Engineering Office
Project Engineer N/A
Project Inspector N/A
Materials Engineer N/A
Approving Authority N/A

Contractor Authorities

Contractor HAUSLAND CONSTRUCTION (32378)
Project Manager N/A
Project Engineer N/A
Materials Engineer N/A

Financial Information

Source of Funds Regular Infra - GAA 2025 OO-2
Contract Cost ₱37,622,683.82

Contract Duration

Effectivity Date February 17, 2025
Original Expiry Date September 04, 2025
Contract Duration 200 days
Days Remaining Expired (88 days ago)

Status & Progress

Current Status Completed
Accomplishment 100.00%

Record Information

Created At November 26, 2025 03:31 AM
Last Updated November 26, 2025 03:31 AM