Status On-Going
Accomplishment 44.89%
Contract Cost ₱29.4M
Contract Duration 155 days

Project Progress

44.89%

Basic Information

Contract ID 25HM0021
Infrastructure Year 2025
Description OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM, REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS, LUYANG-POO-LAZI RD - K0020+000 - K0020+850

Implementing Office Authorities

Region NIR - Negros Island Region
Implementing Office Siquijor District Engineering Office
Project Engineer N/A
Project Inspector N/A
Materials Engineer N/A
Approving Authority N/A

Contractor Authorities

Contractor FROY J BUILDERS & SUPPLIES (43675)
Project Manager N/A
Project Engineer N/A
Materials Engineer N/A

Financial Information

Source of Funds Regular Infra - GAA 2025 OO-1
Contract Cost ₱29,403,440.08

Contract Duration

Effectivity Date February 20, 2025
Original Expiry Date July 24, 2025
Contract Duration 155 days
Days Remaining Expired (130 days ago)

Status & Progress

Current Status On-Going
Accomplishment 44.89%

Record Information

Created At November 26, 2025 03:09 AM
Last Updated November 26, 2025 03:09 AM