Basic Information
Contract ID
25PB0012
Infrastructure Year
2025
Description
ORGANIZATIONAL OUTCOME 2 - PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF FLOOD CONTROL STRUCTURE
Implementing Office Authorities
Region
CAR - Cordillera Administrative Region
Implementing Office
Apayao 1st District Engineering Office
Project Engineer
N/A
Project Inspector
N/A
Materials Engineer
N/A
Approving Authority
N/A
Contractor Authorities
Contractor
OMENGAN CONSTRUCTION & DEVELOPMENT CORPORATION (5119)
Project Manager
N/A
Project Engineer
N/A
Materials Engineer
N/A
Financial Information
Source of Funds
Regular Infra - GAA 2025 OO-2
Contract Cost
₱108,755,500.02
Contract Duration
Effectivity Date
March 26, 2025
Original Expiry Date
May 14, 2026
Contract Duration
415 days
Days Remaining
163 days remaining
Status & Progress
Current Status
On-Going
Accomplishment
84.91%
Record Information
Created At
November 25, 2025 02:22 PM
Last Updated
November 25, 2025 02:22 PM