Status On-Going
Accomplishment 11.37%
Contract Cost ₱142.5M
Contract Duration 297 days

Project Progress

11.37%

Basic Information

Contract ID 25HK0018
Infrastructure Year 2025
Description SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 - INSTALLATION/APPLICATION OF ROAD SAFETY FACILITIES (ROADWAY LIGHTING) ALONG STA. CATALINA - PAMPLONA - TANJAY CITY - K0034+000 - K0046+000

Implementing Office Authorities

Region NIR - Negros Island Region
Implementing Office Negros Oriental 2nd District Engineering Office
Project Engineer N/A
Project Inspector N/A
Materials Engineer N/A
Approving Authority N/A

Contractor Authorities

Contractor ROCK-WBL CONSTRUCTION CORP. (FOR: ROCK-WBL CONSTRUCTION TRADING & SERVICES) (44551)
Project Manager N/A
Project Engineer N/A
Materials Engineer N/A

Financial Information

Source of Funds Regular Infra - GAA 2025 SSP
Contract Cost ₱142,493,390.58

Contract Duration

Effectivity Date February 20, 2025
Original Expiry Date December 13, 2025
Contract Duration 297 days
Days Remaining 11 days remaining

Status & Progress

Current Status On-Going
Accomplishment 11.37%

Record Information

Created At November 26, 2025 02:45 AM
Last Updated November 26, 2025 02:45 AM