Status On-Going
Accomplishment 100.00%
Contract Cost ₱82.0M
Contract Duration 345 days

Project Progress

100.00%

Basic Information

Contract ID 25PB0029
Infrastructure Year 2025
Description CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP)-BIP-FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF MATALAG (DOWNSTREAM) FLOOD MITIGATION STRUCTURES, STA.33+288-STA.34+248

Implementing Office Authorities

Region CAR - Cordillera Administrative Region
Implementing Office Apayao 1st District Engineering Office
Project Engineer N/A
Project Inspector N/A
Materials Engineer N/A
Approving Authority N/A

Contractor Authorities

Contractor JOMARCANN GENERAL CONSTRUCTION (30599)
Project Manager N/A
Project Engineer N/A
Materials Engineer N/A

Financial Information

Source of Funds Regular Infra - GAA 2025 SSP
Contract Cost ₱82,029,029.29

Contract Duration

Effectivity Date April 08, 2025
Original Expiry Date March 18, 2026
Contract Duration 345 days
Days Remaining 106 days remaining

Status & Progress

Current Status On-Going
Accomplishment 100.00%

Record Information

Created At November 25, 2025 02:16 PM
Last Updated November 25, 2025 02:16 PM