Status On-Going
Accomplishment 56.37%
Contract Cost ₱75.9M
Contract Duration 237 days

Project Progress

56.37%

Basic Information

Contract ID 25HJ0156
Infrastructure Year 2025
Description ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ROAD WIDENING ALONG PRIMARY ROAD - DUMAGUETE NORTH ROAD (JCY BAIS - KABANKALAN - NEGROS OCC BDRY) K0125+380 - K0125+719, K0125+933 - K0126+933, GUIHULNGAN CITY, NEGROS ORIENTAL

Implementing Office Authorities

Region NIR - Negros Island Region
Implementing Office Negros Oriental 1st District Engineering Office
Project Engineer N/A
Project Inspector N/A
Materials Engineer N/A
Approving Authority N/A

Contractor Authorities

Contractor JM COLLERA KONSTRACT (42258)
Project Manager N/A
Project Engineer N/A
Materials Engineer N/A

Financial Information

Source of Funds Regular Infra - GAA 2025 OO-1
Contract Cost ₱75,900,096.43

Contract Duration

Effectivity Date March 27, 2025
Original Expiry Date November 18, 2025
Contract Duration 237 days
Days Remaining Expired (13 days ago)

Status & Progress

Current Status On-Going
Accomplishment 56.37%

Record Information

Created At November 26, 2025 02:41 AM
Last Updated November 26, 2025 02:41 AM