Status On-Going
Accomplishment 96.44%
Contract Cost ₱100.9M
Contract Duration 266 days

Project Progress

96.44%

Basic Information

Contract ID 25GQ0006
Infrastructure Year 2025
Description ROAD WIDENING ALONG BACOLOD NORTH RD (S00425NR) - K0135+898 - K0139+053

Implementing Office Authorities

Region NIR - Negros Island Region
Implementing Office Negros Occidental 5th District Engineering Office
Project Engineer N/A
Project Inspector N/A
Materials Engineer N/A
Approving Authority N/A

Contractor Authorities

Contractor KENNETH CONSTRUCTION AND GENERAL MERCHANDISE (33441)
Project Manager N/A
Project Engineer N/A
Materials Engineer N/A

Financial Information

Source of Funds Regular Infra - GAA 2025 OO-1
Contract Cost ₱100,886,247.12

Contract Duration

Effectivity Date March 27, 2025
Original Expiry Date December 17, 2025
Contract Duration 266 days
Days Remaining 15 days remaining

Status & Progress

Current Status On-Going
Accomplishment 96.44%

Record Information

Created At November 26, 2025 02:30 AM
Last Updated November 26, 2025 02:30 AM