Status Completed
Accomplishment 100.00%
Contract Cost ₱11.1M
Contract Duration 92 days

Project Progress

100.00%

Basic Information

Contract ID 25GQ0003
Infrastructure Year 2025
Description RECONSTRUCTION TO CONCRETE PAVEMENT ALONG BACOLOD-MURCIA-DS BENEDICTO-SN CARLOS CITY RD (S00427NR) - K0070+332 - K0070+807

Implementing Office Authorities

Region NIR - Negros Island Region
Implementing Office Negros Occidental 5th District Engineering Office
Project Engineer N/A
Project Inspector N/A
Materials Engineer N/A
Approving Authority N/A

Contractor Authorities

Contractor JVC TOUGH CORE CONSTRUCTION & BUILDERS CORP. (43493)
Project Manager N/A
Project Engineer N/A
Materials Engineer N/A

Financial Information

Source of Funds Regular Infra - GAA 2025 OO-1
Contract Cost ₱11,114,020.29

Contract Duration

Effectivity Date March 03, 2025
Original Expiry Date June 02, 2025
Contract Duration 92 days
Days Remaining Expired (182 days ago)

Status & Progress

Current Status Completed
Accomplishment 100.00%

Record Information

Created At November 26, 2025 02:28 AM
Last Updated November 26, 2025 02:28 AM