Status On-Going
Accomplishment 96.45%
Contract Cost ₱43.5M
Contract Duration 230 days

Project Progress

96.45%

Basic Information

Contract ID 25PB0008
Infrastructure Year 2025
Description ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF FLOOD CONTROL STRUCTURE AL

Implementing Office Authorities

Region CAR - Cordillera Administrative Region
Implementing Office Apayao 1st District Engineering Office
Project Engineer N/A
Project Inspector N/A
Materials Engineer N/A
Approving Authority N/A

Contractor Authorities

Contractor ASC CONSTRUCTION & CONCRETE PRODUCTS (26788)
Project Manager N/A
Project Engineer N/A
Materials Engineer N/A

Financial Information

Source of Funds Regular Infra - GAA 2025 OO-2
Contract Cost ₱43,524,844.49

Contract Duration

Effectivity Date March 24, 2025
Original Expiry Date November 08, 2025
Contract Duration 230 days
Days Remaining Expired (23 days ago)

Status & Progress

Current Status On-Going
Accomplishment 96.45%

Record Information

Created At November 25, 2025 02:13 PM
Last Updated November 25, 2025 02:13 PM