Status Completed
Accomplishment 100.00%
Contract Cost ₱14.5M
Contract Duration 76 days

Project Progress

100.00%

Basic Information

Contract ID 25GN0001
Infrastructure Year 2025
Description INSTALLATION/APPLICATION OF ROAD SAFETY FACILITIES (ROADWAY LIGHTING) ALONG BACOLOD SOUTH BY-PASS ROAD - K0019+144 - K0020+420

Implementing Office Authorities

Region NIR - Negros Island Region
Implementing Office Negros Occidental 4th District Engineering Office
Project Engineer N/A
Project Inspector N/A
Materials Engineer N/A
Approving Authority N/A

Contractor Authorities

Contractor JAIME B. CHING ENTERPRISES (4256)
Project Manager N/A
Project Engineer N/A
Materials Engineer N/A

Financial Information

Source of Funds Regular Infra - GAA 2025 SSP
Contract Cost ₱14,519,279.59

Contract Duration

Effectivity Date April 03, 2025
Original Expiry Date June 17, 2025
Contract Duration 76 days
Days Remaining Expired (167 days ago)

Status & Progress

Current Status Completed
Accomplishment 100.00%

Record Information

Created At November 26, 2025 02:15 AM
Last Updated November 26, 2025 02:15 AM