Status On-Going
Accomplishment 55.67%
Contract Cost ₱96.5M
Contract Duration 223 days

Project Progress

55.67%

Basic Information

Contract ID 25GL0100
Infrastructure Year 2025
Description PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY -VALLEHERMOSO-CANLAON CITY-LA CASTELLANA RD - K0076+500 -K0079+132

Implementing Office Authorities

Region NIR - Negros Island Region
Implementing Office Negros Occidental 2nd District Engineering Office
Project Engineer N/A
Project Inspector N/A
Materials Engineer N/A
Approving Authority N/A

Contractor Authorities

Contractor UY CONDEV CORPORATION (FORMERLY:UY CONSTRUCTION & (12336)
Project Manager N/A
Project Engineer N/A
Materials Engineer N/A

Financial Information

Source of Funds Regular Infra - GAA 2025 OO-1
Contract Cost ₱96,499,781.64

Contract Duration

Effectivity Date June 03, 2025
Original Expiry Date January 11, 2026
Contract Duration 223 days
Days Remaining 40 days remaining

Status & Progress

Current Status On-Going
Accomplishment 55.67%

Record Information

Created At November 26, 2025 02:05 AM
Last Updated November 26, 2025 02:05 AM