Status Completed
Accomplishment 100.00%
Contract Cost ₱31.8M
Contract Duration 136 days

Project Progress

100.00%

Basic Information

Contract ID 25GL0002
Infrastructure Year 2025
Description RECONSTRUCTION TO CONCRETE PAVEMENT - HINIGARAN-ISABELA RD K0067 + 424 - K0068 + 517

Implementing Office Authorities

Region NIR - Negros Island Region
Implementing Office Negros Occidental 2nd District Engineering Office
Project Engineer N/A
Project Inspector N/A
Materials Engineer N/A
Approving Authority N/A

Contractor Authorities

Contractor KENNETH CONSTRUCTION AND GENERAL MERCHANDISE (33441)
Project Manager N/A
Project Engineer N/A
Materials Engineer N/A

Financial Information

Source of Funds Regular Infra - GAA 2025 OO-1
Contract Cost ₱31,798,060.00

Contract Duration

Effectivity Date March 27, 2025
Original Expiry Date August 09, 2025
Contract Duration 136 days
Days Remaining Expired (114 days ago)

Status & Progress

Current Status Completed
Accomplishment 100.00%

Record Information

Created At November 26, 2025 01:59 AM
Last Updated November 26, 2025 01:59 AM