Basic Information
Contract ID
25GK0030
Infrastructure Year
2025
Description
PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - BACOLOD NORTH RD - K0036 + 000 - K0036 + 902
Implementing Office Authorities
Region
NIR - Negros Island Region
Implementing Office
Negros Occidental 1st District Engineering Office
Project Engineer
N/A
Project Inspector
N/A
Materials Engineer
N/A
Approving Authority
N/A
Contractor Authorities
Contractor
HOMEWORLD CONSTRUCTION CORP. (FORMERLY HOMEWORLD E (14725)
Project Manager
N/A
Project Engineer
N/A
Materials Engineer
N/A
Financial Information
Source of Funds
Regular Infra - GAA 2025 OO-1
Contract Cost
₱42,610,653.48
Contract Duration
Effectivity Date
March 03, 2025
Original Expiry Date
June 11, 2025
Contract Duration
101 days
Days Remaining
Expired (173 days ago)
Status & Progress
Current Status
Completed
Accomplishment
100.00%
Record Information
Created At
November 26, 2025 01:45 AM
Last Updated
November 26, 2025 01:45 AM