Status On-Going
Accomplishment 52.98%
Contract Cost ₱141.6M
Contract Duration 210 days

Project Progress

52.98%

Basic Information

Contract ID 25GO0141
Infrastructure Year 2025
Description PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY BACOLOD CIRCUMFERENTIAL RD - K0003 + (-535) - K0006 +000

Implementing Office Authorities

Region NIR - Negros Island Region
Implementing Office Bacolod City District Engineering Office
Project Engineer N/A
Project Inspector N/A
Materials Engineer N/A
Approving Authority N/A

Contractor Authorities

Contractor IBC INTERNATIONAL BUILDERS CORPORATION (8576)
Project Manager N/A
Project Engineer N/A
Materials Engineer N/A

Financial Information

Source of Funds Regular Infra - GAA 2025 OO-1
Contract Cost ₱141,619,951.94

Contract Duration

Effectivity Date May 27, 2025
Original Expiry Date December 22, 2025
Contract Duration 210 days
Days Remaining 20 days remaining

Status & Progress

Current Status On-Going
Accomplishment 52.98%

Record Information

Created At November 26, 2025 01:43 AM
Last Updated November 26, 2025 01:43 AM