Basic Information
Contract ID
25H00053
Infrastructure Year
2025
Description
CONVERGENCE AND SPECIAL SUPPORT PROGRAM: BASIC INFRASTRUCTURE PROGRAM (BIP), FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES, CONSTRUCTION OF SEAWALL, BARANGAY NORTH POBLACION, JIMALALUD, NEGROS ORIENTAL
Implementing Office Authorities
Region
NIR - Negros Island Region
Implementing Office
Negros Island Region
Project Engineer
N/A
Project Inspector
N/A
Materials Engineer
N/A
Approving Authority
N/A
Contractor Authorities
Contractor
PHILSOUTH BUILDERS INC (FORMERLY:PHILSOUTH BUILDERS) (21962)
Project Manager
N/A
Project Engineer
N/A
Materials Engineer
N/A
Financial Information
Source of Funds
Regular Infra - GAA 2025 SSP
Contract Cost
₱149,649,360.00
Contract Duration
Effectivity Date
March 27, 2025
Original Expiry Date
March 21, 2026
Contract Duration
360 days
Days Remaining
109 days remaining
Status & Progress
Current Status
On-Going
Accomplishment
40.69%
Record Information
Created At
November 26, 2025 01:27 AM
Last Updated
November 26, 2025 01:27 AM