Basic Information
Contract ID
25G00070
Infrastructure Year
2025
Description
CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG MINULU- AN RIVER (BOTHSTREAM) AT BACOLOD NORTH RD, TALISAY CITY, NEGROS OCCIDENTAL
Implementing Office Authorities
Region
NIR - Negros Island Region
Implementing Office
Negros Island Region
Project Engineer
N/A
Project Inspector
N/A
Materials Engineer
N/A
Approving Authority
N/A
Contractor Authorities
Contractor
HOMEWORLD CONSTRUCTION CORP. (FORMERLY HOMEWORLD E (14725)
Project Manager
N/A
Project Engineer
N/A
Materials Engineer
N/A
Financial Information
Source of Funds
Regular Infra - GAA 2025 OO-2
Contract Cost
₱179,682,935.50
Contract Duration
Effectivity Date
March 18, 2025
Original Expiry Date
April 18, 2026
Contract Duration
397 days
Days Remaining
137 days remaining
Status & Progress
Current Status
On-Going
Accomplishment
0.00%
Record Information
Created At
November 26, 2025 01:21 AM
Last Updated
November 26, 2025 01:21 AM