Status On-Going
Accomplishment 0.00%
Contract Cost ₱179.7M
Contract Duration 397 days

Project Progress

0.00%

Basic Information

Contract ID 25G00070
Infrastructure Year 2025
Description CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG MINULU- AN RIVER (BOTHSTREAM) AT BACOLOD NORTH RD, TALISAY CITY, NEGROS OCCIDENTAL

Implementing Office Authorities

Region NIR - Negros Island Region
Implementing Office Negros Island Region
Project Engineer N/A
Project Inspector N/A
Materials Engineer N/A
Approving Authority N/A

Contractor Authorities

Contractor HOMEWORLD CONSTRUCTION CORP. (FORMERLY HOMEWORLD E (14725)
Project Manager N/A
Project Engineer N/A
Materials Engineer N/A

Financial Information

Source of Funds Regular Infra - GAA 2025 OO-2
Contract Cost ₱179,682,935.50

Contract Duration

Effectivity Date March 18, 2025
Original Expiry Date April 18, 2026
Contract Duration 397 days
Days Remaining 137 days remaining

Status & Progress

Current Status On-Going
Accomplishment 0.00%

Record Information

Created At November 26, 2025 01:21 AM
Last Updated November 26, 2025 01:21 AM