Status On-Going
Accomplishment 29.93%
Contract Cost ₱94.8M
Contract Duration 342 days

Project Progress

29.93%

Basic Information

Contract ID 25OF0091
Infrastructure Year 2025
Description IMPROVEMENT OF ROAD AT BARANGAY FAIRVIEW, QUEZON CITY

Implementing Office Authorities

Region NCR - National Capital Region
Implementing Office Quezon City 1st District Engineering Office
Project Engineer N/A
Project Inspector N/A
Materials Engineer N/A
Approving Authority N/A

Contractor Authorities

Contractor LE BRON CONSTRUCTION (32219)
Project Manager N/A
Project Engineer N/A
Materials Engineer N/A

Financial Information

Source of Funds Regular Infra - GAA 2025 SSP
Contract Cost ₱94,762,793.95

Contract Duration

Effectivity Date March 03, 2025
Original Expiry Date February 07, 2026
Contract Duration 342 days
Days Remaining 67 days remaining

Status & Progress

Current Status On-Going
Accomplishment 29.93%

Record Information

Created At November 26, 2025 12:53 AM
Last Updated November 26, 2025 12:53 AM