Status On-Going
Accomplishment 7.43%
Contract Cost ₱122.5M
Contract Duration 360 days

Project Progress

7.43%

Basic Information

Contract ID 25OF0059
Infrastructure Year 2025
Description CONSTRUCTION OF MULTI-PURPOSE BUILDING (BUILDING 1), BARANGAY BAHAY TORO, QUEZON CITY

Implementing Office Authorities

Region NCR - National Capital Region
Implementing Office Quezon City 1st District Engineering Office
Project Engineer N/A
Project Inspector N/A
Materials Engineer N/A
Approving Authority N/A

Contractor Authorities

Contractor DUMDUMA CONSTRUCTION AND TRADING CORPORATION (37256)
Project Manager N/A
Project Engineer N/A
Materials Engineer N/A

Financial Information

Source of Funds Regular Infra - GAA 2025 SSP
Contract Cost ₱122,512,138.55

Contract Duration

Effectivity Date June 30, 2025
Original Expiry Date June 24, 2026
Contract Duration 360 days
Days Remaining 204 days remaining

Status & Progress

Current Status On-Going
Accomplishment 7.43%

Record Information

Created At November 26, 2025 12:50 AM
Last Updated November 26, 2025 12:50 AM