Status Completed
Accomplishment 100.00%
Contract Cost ₱95.5M
Contract Duration 210 days

Project Progress

100.00%

Basic Information

Contract ID 25OF0037
Infrastructure Year 2025
Description PREVENTIVE MAINTENANCE - SECONDARY ROADS - A BONIFACIO AVE - K0006+(-348) - K0007+280, QUEZON CITY

Implementing Office Authorities

Region NCR - National Capital Region
Implementing Office Quezon City 1st District Engineering Office
Project Engineer N/A
Project Inspector N/A
Materials Engineer N/A
Approving Authority N/A

Contractor Authorities

Contractor L.R. TIQUI BUILDERS, INC. (13810)
Project Manager N/A
Project Engineer N/A
Materials Engineer N/A

Financial Information

Source of Funds Regular Infra - GAA 2025 OO-1
Contract Cost ₱95,524,991.99

Contract Duration

Effectivity Date February 19, 2025
Original Expiry Date September 16, 2025
Contract Duration 210 days
Days Remaining Expired (76 days ago)

Status & Progress

Current Status Completed
Accomplishment 100.00%

Record Information

Created At November 26, 2025 12:44 AM
Last Updated November 26, 2025 12:44 AM