Status Completed
Accomplishment 100.00%
Contract Cost ₱142.1M
Contract Duration 150 days

Project Progress

100.00%

Basic Information

Contract ID 25OE0040
Infrastructure Year 2025
Description INSTALLATION OF PUMP ACCESSORIES ALONG ESTERO DE SAN MIGUEL, MANILA CITY

Implementing Office Authorities

Region NCR - National Capital Region
Implementing Office North Manila District Engineering Office
Project Engineer N/A
Project Inspector N/A
Materials Engineer N/A
Approving Authority N/A

Contractor Authorities

Contractor EIGHT J'S CONSTRUCTION SERVICES (41912) / MNJAP CONSTRUCTION SERVICES (56648)
Project Manager N/A
Project Engineer N/A
Materials Engineer N/A

Financial Information

Source of Funds Regular Infra - GAA 2025 OO-2
Contract Cost ₱142,144,438.69

Contract Duration

Effectivity Date February 14, 2025
Original Expiry Date July 13, 2025
Contract Duration 150 days
Days Remaining Expired (141 days ago)

Status & Progress

Current Status Completed
Accomplishment 100.00%

Record Information

Created At November 26, 2025 12:35 AM
Last Updated November 26, 2025 12:35 AM