Basic Information
Contract ID
25OE0078
Infrastructure Year
2025
Description
REHABILITATION OF ROAD WITH DRAINAGE IMPROVEMENT WITHIN ZONE 13 TO 24, MANILA CITY (PHASE 3), MANILA CITY
Implementing Office Authorities
Region
NCR - National Capital Region
Implementing Office
North Manila District Engineering Office
Project Engineer
N/A
Project Inspector
N/A
Materials Engineer
N/A
Approving Authority
N/A
Contractor Authorities
Contractor
ALRIE CONSTRUCTION SERVICES (54139)
Project Manager
N/A
Project Engineer
N/A
Materials Engineer
N/A
Financial Information
Source of Funds
Regular Infra - GAA 2025 SSP
Contract Cost
₱141,843,652.14
Contract Duration
Effectivity Date
May 16, 2025
Original Expiry Date
October 31, 2025
Contract Duration
169 days
Days Remaining
Expired (31 days ago)
Status & Progress
Current Status
Completed
Accomplishment
100.00%
Record Information
Created At
November 26, 2025 12:32 AM
Last Updated
November 26, 2025 12:32 AM