Basic Information
Contract ID
25PA0001
Infrastructure Year
2025
Description
SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF BRIDGE, SINALANG-PALAO, BANGUED, ABRA, BANGUED, ABRA
Implementing Office Authorities
Region
CAR - Cordillera Administrative Region
Implementing Office
Abra District Engineering Office
Project Engineer
N/A
Project Inspector
N/A
Materials Engineer
N/A
Approving Authority
N/A
Contractor Authorities
Contractor
739 BUILDERS (31174)
Project Manager
N/A
Project Engineer
N/A
Materials Engineer
N/A
Financial Information
Source of Funds
Regular Infra - GAA 2025 SSP
Contract Cost
₱18,682,040.62
Contract Duration
Effectivity Date
March 19, 2025
Original Expiry Date
September 26, 2025
Contract Duration
192 days
Days Remaining
Expired (66 days ago)
Status & Progress
Current Status
On-Going
Accomplishment
64.41%