Status On-Going
Accomplishment 64.41%
Contract Cost ₱18.7M
Contract Duration 192 days

Project Progress

64.41%

Basic Information

Contract ID 25PA0001
Infrastructure Year 2025
Description SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF BRIDGE, SINALANG-PALAO, BANGUED, ABRA, BANGUED, ABRA

Implementing Office Authorities

Region CAR - Cordillera Administrative Region
Implementing Office Abra District Engineering Office
Project Engineer N/A
Project Inspector N/A
Materials Engineer N/A
Approving Authority N/A

Contractor Authorities

Contractor 739 BUILDERS (31174)
Project Manager N/A
Project Engineer N/A
Materials Engineer N/A

Financial Information

Source of Funds Regular Infra - GAA 2025 SSP
Contract Cost ₱18,682,040.62

Contract Duration

Effectivity Date March 19, 2025
Original Expiry Date September 26, 2025
Contract Duration 192 days
Days Remaining Expired (66 days ago)

Status & Progress

Current Status On-Going
Accomplishment 64.41%

Record Information

Created At November 25, 2025 01:53 PM
Last Updated November 25, 2025 01:53 PM